Timeline of 65 Martin Place Project
2018 – Project Inception
						Initial Planning Begins
						
						RBA begins scoping a refurbishment of its Sydney headquarters at 65 Martin Place
					
Scope
- Upgrade base building to current compliance
 - Create new workspace for operational needs
 
Assumptions
- Minimal asbestos (noting major remediation in the 1990s)
 - Facade to be retained
 - No material impact on basement operations
 - Bank expected to remain in occupation during renovations.
 
2019–2020 – Feasibility Study and Submission to Parliament
Design Phase
					Early concept architectural and engineering assessments
Options Considered
- Three options to renovate in place
 - One option to relocate entirely
 
Decision
						
Proceed with integrated renovation of the whole building as the most cost-effective long-term solution
Parliamentary Approval
						
March 2020
Initial Cost Estimate
						
Approx. $260 million.
2021–2022 – Design and Procurement Phase
Design Phase
- Full documentation including side core, new services infrastructure, new window glazing, and fit-out
 - Lifts and facade to remain
 
Procurement Phase
- Tender to Head Contractors
 - Built appointed as Head Contractor in March 2022
 
Construction Begins
						April 2022
Asbestos Discovery
						Late 2022, signs of more asbestos than expected; construction resequencing begins.
2023 – Latent Conditions Revealed and Scope Expanded
Asbestos Issues
- 4–5 times more asbestos than typical for buildings of its era
 - Found in beams, slabs, soffits, facade, and service panels
 - Requires full strip-back to steel frame
 
Other Latent Conditions
					
Fire stairs and lift shafts non-compliant with modern safety codes
Options Analysis
- Continue construction and rebuild to heritage guidelines
 - Sell the building and lease back
 - Sell the building and lease elsewhere
 - Sell the building and buy elsewhere
 
Decision
						Continue construction as most cost-efficient and compliant with Commonwealth Heritage requirements
Revised Cost Estimate
						
$1.089 billion
Timeline Extended
						
Completion pushed from 2025 to November 2029.
2024 – Relocation and New Procurement
Staff Relocation
						
RBA staff moved to leased space at 8 Chifley Square
Critical Functions
- Data Centre, Banknotes, and Archives Storage decommissioned
 - Alternative sites established
 
Additional Costs
					
Office rental: $108.8 million over 6 years
Procurement Update
- New two-stage approach due to project size and scope
 - Built engaged for Stage 1 (demolition) in March 2025.
 
August 2025 – Current Status
Project Phases
- Closeout of Initial Project: $208.8 million
 - Stage 1 – Demolition & Remediation
 - Stage 2A – New Build: Planning underway
 - Stage 2B – Fit-out: To follow
 
Estimated Cost
					Asbestos removal, demolition, and rebuilding now approximately $1.2 billion
Next Milestones
- Governance Board approval for next stages
 - Continued reporting on cost, risk, and timeline.